Neyr Perse, the oil and gas subsidiary of MAPNA Group, has achieved a new record in the field by completing a major shutdown for repairs in the South Pars Phase 14 Refinery in a short time.
The shutdown was necessary to ensure stable gas production during the winter season, when the gas demand in the country increases. The shutdown also aimed to address the production challenges and improve the efficiency of the refinery.
The South Pars Phase 14 Refinery, which has been operational since 2022, underwent a comprehensive update during the shutdown.
The project was carried out with meticulous coordination, involving Neyr Perse specialists who worked around the clock for five days and nights. The project involved 1029 repair and maintenance activities, of which 85% were completed within the planned timeframe.
Neyr Perse Company, which is in charge of the South Pars Phase 14 Refinery project, is responsible for a range of activities, including engineering, procurement, construction, installation, and operation of various units in the refinery. These units include compressors, measurement stations, sulfur recovery and granulation units, electricity distribution, steam production, fueling systems, air supply and distribution, instrumentation, nitrogen production, sea water transfer equipment, booster pumps, water packages, diesel, cooling water packages, water and wastewater treatment, sulfur storage tanks, chemicals, and electrical systems.