Tous Power Plant: MAPNA Receives PAC for 2nd Steam Unit

MAPNA Group has received the Provisional Acceptance Certificate (PAC) for the second steam unit of the Tous (Ferdowsi) Combined Cycle Power Plant on October 22, 2023.

The construction of this power plant was carried out based on an Energy Conversion Agreement (ECA) and in the form of Build, Own, and Operate (BOO) between MAPNA Tous Power Generation Company (acting on behalf of MAPNA) and Thermal Power Plants Holding Company.
As per the terms of the contract, the Ministry of Energy is obligated to reimburse the investor with the saved amount of liquid fuel (or its equivalent cash value) resulting from the conversion of the plant into a combined cycle facility. The Ministry of Energy has a maximum period of two years to fulfill this obligation, subject to the investment limit.
The scope of the combined cycle project encompasses the installation of three E-type steam turbines and generators, each with a nominal capacity of 160 MW, along with six Heat Recovery Steam Generators (HRSGs), three Air Cooled Condenser (ACC) cooling system units, the Balance of Plant (BOP), and a 400-kV substation.
Situated at the 25th kilometer of the Mashhad-Quchan road in the northeastern Khorasan Province, the power plant is operated by MAPNA Tous Power Generation Company. The project was executed under an Engineering, Procurement, and Construction (EPC) scheme by MAPNA Power Plant Construction and Development Company (MD-1).

Share:
Scroll to Top