The second unit of Mahshahr thermal power plant received final acceptance certificate (FAC) on Saturday, December 28, 2019. With provisional delivery of this unit, MD-2 has now received PAC for 82 units with an aggregate capacity of 12,369 MWs.
Located 9 kilometers north of Mahshahr on Jarrahi (Chamran) road, Mahshahr power plant includes four gas-fired units each with a capacity of 162 MWs.
Thermal Power Plants Holding Company is the client of the project and Ghods Niroo Engineering Company serves as the consultant.