185-MW Upgraded Gas Units

upgrading gas units to 185 mw of power production

Conducted activities:

 

  • The first phase ofthe project(accessto173MW of power production capacity) has been fulfilled under ISO conditions and necessary modifications of the cooling system have been applied to the sites of selected generators.

 

  • The second phase ofthe projectconsists ofupgrading todetailed design. Detailed design calculations for an upgrade to 185 MW of power output have been completed and the procedures for purchasing new materialsforinsulation systemsare being carried out.